• facebook
  • whatsapp
  • telegram

Time and Work

Work is always taken as one unit. Construction of a building, filling water in the tank, painting a room etc.
To complete a job, a man will do the same amount of work on each day of the total number of days he takes to complete that job.
If a man can do a piece of work in 8 days, then his one day’s work is .
If a man’s one day’s work is  then he can complete the total work in 4 days.
If a man can complete a piece of work in A days and another man can complete the  same work in B days,
         then they together can complete the work in   days.
         Similarly, three persons A, B and C together can complete in   days.

Ex: A can complete a piece of work in 6 days and B in 8 days. In what time they complete if they work together?


 

MAN DAYS: 
     If 6 men can complete a work in 4 days, then the number of man days required to complete that work is 6 × 4 = 24.
     Whatever may be the number of persons working on that, the total number of man days required for that work will be 24.

 

Ex:18 men together can complete a work in 14 days. In how many days 12 men finish that work?      

A) 5 dyas                 B) 6 days               C) 10 days                D) 8 days               E) None of these


      Men and Time are inversely proportional i.e., when more men work, they take less time to complete the work. Similarly when less men work, they take more time to complete the work.
       Men and Work are directly proportional i.e., when more men are there, they do more work and less men are there, they do less work.
     Similarly, Time and Work are also directly proportional. If men work for more time then they do more work and less time then the work is also less.
     The relation among these variables can be shown in a formula
     If M is Men, D is Days (Time) and W is work then 


 

Ex:  A contractor employs 12 men to complete a work in 15 days. But after 8days he notices that only 30% work has been completed. In order to finish the work in the given time, how many more men he has to recruit?
A) 32             B) 24                C) 20                D) 9               E) None of these



     
    To complete the remaining work 32 men are required
    Additional men required 32 - 12 = 20
        Hence answer is (c)   

Posted Date : 07-02-2021

గమనిక : ప్రతిభ.ఈనాడు.నెట్‌లో కనిపించే వ్యాపార ప్రకటనలు వివిధ దేశాల్లోని వ్యాపారులు, సంస్థల నుంచి వస్తాయి. మరి కొన్ని ప్రకటనలు పాఠకుల అభిరుచి మేరకు కృత్రిమ మేధస్సు సాంకేతికత సాయంతో ప్రదర్శితమవుతుంటాయి. ఆ ప్రకటనల్లోని ఉత్పత్తులను లేదా సేవలను పాఠకులు స్వయంగా విచారించుకొని, జాగ్రత్తగా పరిశీలించి కొనుక్కోవాలి లేదా వినియోగించుకోవాలి. వాటి నాణ్యత లేదా లోపాలతో ఈనాడు యాజమాన్యానికి ఎలాంటి సంబంధం లేదు. ఈ విషయంలో ఉత్తర ప్రత్యుత్తరాలకు, ఈ-మెయిల్స్ కి, ఇంకా ఇతర రూపాల్లో సమాచార మార్పిడికి తావు లేదు. ఫిర్యాదులు స్వీకరించడం కుదరదు. పాఠకులు గమనించి, సహకరించాలని మనవి.

 

study-material-:-group-d

Previous Papers

 

విద్యా ఉద్యోగ సమాచారం

 

Model Papers

 

లేటెస్ట్ నోటిఫికేష‌న్స్‌